We haven't got much time left and the other courses have sprung alot of last minute projects and assignments on us. So I had a meeting with Muchacha to finalise the modules that we would develop and which ones we would drop from the project (EL can pay for them if they still want them after our FYP is over).

It's time to turn up the heat and GIT PROGRAMMIN!

Need a light?

Here's a breakdown of the remaining modules we need to develop (and the rough estimate of time needed to do them):

Flash based stuff
1. Flash AI help - 5 days
2. Flash touch ups - 3 days
3. Flash Multiple additions to class - 3 days
------------

PHP stuff
1. Minor Changes - 1 day
2. Email Prompt + Evaluation - 2-4 days
3. Linkage to IBM DB2 - 2 days
4. Bond Calculation - 2-3 days
5. Data dumping to XLS (indv, dept, company) - 3-4 days
-----------

Stuff we dumped
1. Attendance Taking system - 2 days
2. Employee Details display - 2-3 days